Print View

PROJECT TITLE:

Mechanical Updates and Related Work at Hollywood Elementary School

 

PROJECT#:

26110

 

BRIEF PROJECT DESCRIPTION:

Work includes but is not limited to the installation of new boilers and nit ventilators in the Southern portion of the building. Minor Electrical and Plumbing modifications to be completed to tie new boilers and unit ventilators into existing system. Concrete slab work, wall and floor patching, painting, door and frame replacements, door hardware updates, lighting updates, roofing and other related items will be part of this work. In addition to southern corridors and selective offices flooring, ceiling and LED lighting upgrades as indicated.

 

SCHEDULE:

Out for Bids

June 1, 2026

Mandatory Pre-Bid Meeting

June 17, 2026 at 10:00am

Official Bidders List

June 19, 2026

Bids Due

July 1, 2026 at 3:00 pm

Post Bid Interviews

July 2-7, 2026

Architect Recommendation

July 8, 2026

Owner Awards Project

July 28, 2026

Notice to Proceed Letter

July 29, 2026

All Shop Drawing Reviews Complete

November 30, 2026

Pre-Construction Meeting

TBD

Physical Construction

June 14, 2027 – August 13, 2027

North and South Parking Lot

Reconstruction by Others

June 14, 2027 – August 13, 2027

Substantial Completion

August 13, 2027

Owner Move-in Date

August 18, 2027

Final Completion

September 13, 2027