PROJECT TITLE:
Mechanical Updates and Related Work at Hollywood Elementary School
PROJECT#:
26110
BRIEF PROJECT DESCRIPTION:
Work includes but is not limited to the installation of new boilers and nit ventilators in the Southern portion of the building. Minor Electrical and Plumbing modifications to be completed to tie new boilers and unit ventilators into existing system. Concrete slab work, wall and floor patching, painting, door and frame replacements, door hardware updates, lighting updates, roofing and other related items will be part of this work. In addition to southern corridors and selective offices flooring, ceiling and LED lighting upgrades as indicated.
SCHEDULE:
|
Out for Bids |
June 1, 2026 |
|
Mandatory Pre-Bid Meeting |
June 17, 2026 at 10:00am |
|
Official Bidders List |
June 19, 2026 |
|
Bids Due |
July 1, 2026 at 3:00 pm |
|
Post Bid Interviews |
July 2-7, 2026 |
|
Architect Recommendation |
July 8, 2026 |
|
Owner Awards Project |
July 28, 2026 |
|
Notice to Proceed Letter |
July 29, 2026 |
|
All Shop Drawing Reviews Complete |
November 30, 2026 |
|
Pre-Construction Meeting |
TBD |
|
Physical Construction |
June 14, 2027 – August 13, 2027 |
|
North and South Parking Lot Reconstruction by Others |
June 14, 2027 – August 13, 2027 |
|
Substantial Completion |
August 13, 2027 |
|
Owner Move-in Date |
August 18, 2027 |
|
Final Completion |
September 13, 2027 |