PROJECT TITLE:

Concrete Walk Replacement at B-Wing @ Monroe High School

 

PROJECT #:

26107

 

BRIEF PROJECT DESCRIPTION:

 Removal  and replacement of the concrete walk outside of the B-Wing Entrance Doors at Monroe High School/

 

SCHEDULE:

 

Out for Bids

March 16, 2026

Pre-bid Meeting

April 1, 2026

 

     Monroe High School at 10:00 am

Official Bidders Lis

April 3, 2026

Bids Due

April 15, 2026 @ 3:00 pm

Post Bid Interviews

April 15-21, 2026

Architect Recommendation

April 22, 2026

Owner Awards Project

April 28, 2026

Notice to Proceed Letters

April 29, 2026

All Shop Drawing Reviews Complete

June 10, 2026

Pre-Construction Meeting

June 10, 2026 - Time and Place TBD

Physical Construction

June 15, 2026 – August 14, 2026

Substantial Completion

August 14, 2026

Owner Move-in Date

August 19, 2026

Final Completion

September 14, 2026